- 131active data centre projects
- 78with a lodged planning application
- 7withdrawn, refused or expired
- 80active projects on the map65 at an exact site or official address, 15 approximate (suburb or locality)
Active projects by stage
- 8 under construction
- 77 planned, application lodged
- 46 planned, no application lodged
Of 131 active projects. 7 withdrawn, refused or expired are not included.
By state and territory
Data centre map
The map shows 80 of the 131 active projects. 65 are placed at an exact site or official address. 15 are placed at the centre of their suburb or locality because no exact address could be matched, and have a dashed outline. The other 51 are in the table only.
Use the arrow keys to move between mapped projects. Press Enter to open one.
Status key: Planned (hollow circle on the map) · Under construction (filled teal square on the map) · Withdrawn, refused or expired (not on the map). Planned = proposed or approved, not yet under construction. A dashed outline means the location is approximate (the centre of the suburb or locality).
Boundaries: Australian Bureau of Statistics, ASGS Edition 4 (2026), CC BY 4.0; simplified by Makao.
Data centre projects
138 rows: 131 active projects and 7 withdrawn, refused or expired. 22 rows marked † are in this table but not in the CSV download.
| Project | State | Developer or applicant | Local government area | Status | Stated capacity | Planning application lodged | Verification | Source |
|---|---|---|---|---|---|---|---|---|
| CDC Beard Campus | ACT | CDC Data Centres | Not stated | Under construction | 39 MW (basis not stated) | No | Operator-disclosed only | CDC Data Centres website |
| Hume Campus 3 Data Centre Development (ESO 202600027) | ACT | CDC Data Centres (per w.media) | Not stated | Proposed (ESO rejected; EIS required) | 576 MW (basis not stated) | No | Verified (official source) | ACT ESO 202600027 rejection |
| Hume data centre, Blocks 99 and 103 Section 7 (DA 202443633) | ACT | Not stated in documents opened | Not stated | Approved | Not stated | No | Verified (official source) | ACT DA 202443633 application form |
| 1-5 Khartoum Road Data Centre | NSW | Stockland Development Pty Ltd | City of Ryde | Approved | 35 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-63235720 |
| 192 Narellan Road Data Centre, Campbelltown | NSW | Morehuman Property Group Pty Ltd | Campbelltown | Proposed (in planning) | 100 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-150514738 |
| 23-25 Waterloo Road Data Centre | NSW | Greenbox Architecture Pty Ltd | City of Ryde | Proposed (in planning) | 70 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-91297457 |
| 43-61 Turner Road Data Centre | NSW | ARUP PTY LIMITED | Camden | Approved | 53 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-68013714 |
| 51 Huntingwood Drive Data Centre | NSW | EMKC CUBED MANAGEMENT PTY LTD | Blacktown | Approved | 400 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-41589232 |
| Aldington Road Data Centre | NSW | The Trustee for Fife Land 3 Trust | Penrith | Proposed (in planning) | 444 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-112059740 |
| Apollo Place Data Centre | NSW | EMKC Cubed Management Pty Ltd | Lane Cove | Approved | 45 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-67407231 |
| Ashfords Road Data Centre, Gregadoo | NSW | CDC Data Centres | Wagga Wagga City | Proposed (in planning) | 1,400 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-144289240 |
| Brookhollow Avenue Data Centre Expansion, Norwest | NSW | GreenSquare DC c/- Patch Planning | The Hills Shire | Proposed (in planning) | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-81928961 |
| CDC Data Centre Campus, Kemps Creek | NSW | CDC Data Centres | Penrith | Proposed (in planning) | 1,400 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-133677993 |
| Davis Road Data Centre (Cundall) | NSW | Cundall Johnston and Partners Pty Limited | Fairfield City | Approved | 180 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-59416728 |
| DCI Poplars Data Centre Project | NSW | DCI | Queanbeyan-Palerang Regional | Approved | 25.4 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-64287712 |
| DigiCo SYD1 Data Centre Expansion | NSW | DigiCo | City of Sydney | Approved | 47.5 MW (increase in power consumption only) | Yes | Verified (official source) | NSW Major Projects: SSD-69637456 |
| Eastern Creek Data Centre | NSW | Woolworths Limited | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0108 |
| Eastern Creek Data Centre Expansion Project | NSW | NineZero DC Sub TC I Pty Ltd | Blacktown | Approved | 70.2 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-21342738 |
| EdgeConneX / Stockland MPark Stage 2 | NSW | EdgeConneX | Not stated | Proposed (announced) | 100 MW (basis not stated) | No | Lead only (unverified) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): EdgeConneX / Stockland MPark Stage 2 (CSV) |
| Erskine Park Data Centre | NSW | Woolworths Limited | Penrith | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0109 |
| Frederick Street Data Centre | NSW | Gateway Capital Holdings Pty Ltd | Willoughby City | Proposed (in planning) | 81 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-139545990 |
| Glendenning Road Data Centre | NSW | LEHR CONSULTANTS INTERNATIONAL (AUSTRALIA) PTY LTD | Blacktown | Approved | 202.4 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-73761707 |
| Global Switch Data Facility | NSW | Global Switch | City of Sydney | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0222 |
| Grand Avenue Data Centre Expansion, Rosehill | NSW | Equinix Hyperscale 2 (Sy10) Pty Ltd | City of Parramatta | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-53338465 |
| Hewlett Packard Data Facility | NSW | Hewlett Packard | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP10_0142 |
| Honeman Close Data Centre | NSW | LEHR Consultants International (Australia) Pty Ltd | Blacktown | Approved | 96 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-58601963 |
| Julius Avenue Data Centre | NSW | ISPT PTY LTD | City of Ryde | Proposed (in planning) | 170 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-80018208 |
| Kemps Creek Data Centre | NSW | ARUP PTY LIMITED | Penrith | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10101987 |
| Kurri Kurri Data Centre | NSW | ADW Johnson Pty Limited | Cessnock City | Proposed (in planning) | 550.5 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-128819490 |
| Lanceley Place Data Centre, Artarmon | NSW | Goodman Property Services (AUST) PTY LIMITED | Willoughby City | Approved | 80 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-66777221 |
| Lane Cove West Data Centre | NSW | Greenbox Architecture Pty Ltd | Lane Cove | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-9741 |
| Lucca Road Data Centre Wyong | NSW | DCG Admin Pty Ltd | Central Coast | Proposed (in planning) | 96 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-148199991 |
| Macquarie Data Centres Sydney North 200 MW campus | NSW | Macquarie Data Centres | Not stated | Proposed (announced) | 200 MW (basis not stated) | No | Lead only (unverified) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): Macquarie Data Centres Sydney North 200 MW campus (CSV) |
| Macquarie Engineering and Technology Campus | NSW | MDC NEW SITE SUBTST PTY LTD | City of Ryde | Proposed (in planning) | Not stated | No | Verified (official source) | NSW Major Projects: SSD-151494240 |
| Macquarie IC3 Super West | NSW | Macquarie Data Centres | Not stated | Under construction | 47 MW (basis not stated) | No | Lead only (unverified) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): Macquarie IC3 Super West (CSV) |
| Macquarie Park Data Centre | NSW | Stockland Corporation Ltd | City of Ryde | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10467 |
| Mamre Road Data Centre Campus | NSW | Plan Project Management Pty Ltd | Penrith | Proposed (in planning) | 1,000 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-92743706 |
| Mars Road Data Centre | NSW | Willowtree Planning (NSW) Pty Ltd | Lane Cove | Proposed (in planning) | 140 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-108835458 |
| Marsden Park Data Centre | NSW | CDC Data Centres | Blacktown | Under construction | 504 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-70889211 |
| Mod 4 - Data Centre | NSW | DEXUS Funds Management Limited (proponent of MP 08_0259); facility known as the Fujitsu Data Centre | Cumberland | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0259-Mod-4 |
| NEXTDC S4 Data Centre Horsley Park | NSW | NEXTDC | Fairfield City | Approved | 250 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-63741210 |
| NEXTDC S4 Data Centre Phase 2, Horsley Park | NSW | NEXTDC | Fairfield City | Proposed (in planning) | 134.4 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-108864209 |
| NEXTDC S5 Data Centre and Innovation Hub | NSW | NEXTDC | City of Ryde | Proposed (in planning) | 80 MW (IT capacity) | Yes | Verified (official source) | NSW Major Projects: SSD-63168959 |
| NEXTDC S7 Data Centre, Eastern Creek | NSW | NEXTDC | Blacktown | Proposed (in planning) | 612 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-113934740 |
| Project Apollo Data Centre Macquarie Park | NSW | Goodman Property Services (Aust) Pty Limited | City of Ryde | Approved | 90 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-74069708 |
| Project Atlas Data Centre Eastern Creek | NSW | Goodman Property Services (Aust) Pty Ltd | Blacktown | Proposed (in planning) | 500 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-101067971 |
| Project Duke Data Centre | NSW | Goodman Property Services (Aust) Pty Ltd | Bayside | Approved | 90 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-71368959 |
| Project Echidna Data Centre Eastern Creek | NSW | ARUP AUSTRALIA PTY LTD | Blacktown | Approved | 35 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-47320208 |
| Project Pluto Data Centre | NSW | GOODMAN PROPERTY SERVICES (AUST) PTY LIMITED | Cumberland | Approved | 100 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-69223466 |
| Redbank Data Centre | NSW | IREN | Wagga Wagga City | Proposed (in planning) | 900 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-155572991 |
| Road 1 Data Centre | NSW | Stockland Development Pty Ltd | City of Ryde | Approved | 34.3 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-80814238 |
| Roberts Road Data Centre | NSW | Hindmarsh Construction Australia Pty Ltd | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10330 |
| STACK SYD01 Data Centre, Erskine Park | NSW | STACK Infrastructure | Penrith | Proposed (in planning) | 450 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-82211208 |
| Station Road Data Centre Expansion | NSW | Lehr Consultants International (Australia) Pty Ltd | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-33781208 |
| SYD01 (Huntingwood) Data Centre (EPBC referral) | NSW | Not stated in EPBC layer | Not stated | Proposed (in planning) | Not stated | No | Verified (official source) | EPBC referral 2025/10391 |
| Talavera Road Data Centre Campus Expansion | NSW | Macquarie Data Centres c/‐ GIDDIS Project Management | City of Ryde | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-24299707 |
| Wetherill Park Data Centre | NSW | Stockland | Fairfield City | Proposed (in planning) | 238 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-153190740 |
| NEXTDC D2 Darwin | NT | NEXTDC | Not stated | Listed by operator (no development tag) | 6 MW (basis not stated) | No | Operator-disclosed only | NEXTDC website |
| Project Ares - Integrated Hyperscale Data Centre Campus | NT | Energy North Pty Ltd | Not stated | Proposed (in planning) | 1,000 MW (IT capacity) | No | Verified (official source) | EPBC referral 2026/10560 |
| DigiCo BNE3 | QLD | DigiCo REIT | Not stated | Under construction | 19.6 MW (basis not stated) | No | Operator-disclosed only | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): DigiCo BNE3 (CSV) |
| Latan Data Centre and Renewable Energy Project | QLD | AEWC (Australian Energy and Water Corporation) | Charters Towers Regional | Proposed (announced) | 100 MW (basis not stated) | No | Verified (official source) | Qld North Queensland Major Projects Pipeline |
| NEXTDC Fortitude Valley HQ and data centre expansion (Brisbane A006964285) | QLD | NEXTDC Limited | Brisbane | Approved | Not stated | Yes | Verified (official source) | Brisbane Development.i A006964285 |
| NEXTDC GC1 Gold Coast | QLD | NEXTDC | Not stated | In planning (operator term) | 6 MW (basis not stated) | No | Operator-disclosed only | NEXTDC website |
| NEXTDC SC2 Sunshine Coast | QLD | NEXTDC Limited | Sunshine Coast | Approved; under construction (operator) | 6 MW (basis not stated) | No | Verified (official source) | EDQ development assessment DEV2025/1604 |
| Quinbrook Supernode, Brendale | QLD | Quinbrook Infrastructure Partners | Moreton Bay | Approved (council planning and FIRB, per Qld media statement 8 Jul 2022) | Not stated | No | Verified (official source) | Qld ministerial media statement 95682 (8 Jul 2022) |
| Swanbank data centre, Six Leaf Street (Ipswich 12285/2026/MCU) | QLD | Northern Concept Swanb Pty Ltd | Ipswich | Under assessment | Not stated | Yes | Verified (official source) | Ipswich Development.i 12285/2026/MCU |
| Wellcamp data centre expansion, 65 Witmack Road (Toowoomba MCUC/2016/2385/E) | QLD | Centuria (owner, per ASX results); applicant not confirmed | Toowoomba Regional | Approved (change application, reported) | Not stated | No | Lead only (unverified) | PlanningAlerts: 65 Witmack Road Wellcamp |
| Western Downs Digital Park | QLD | Zerra DC | Western Downs Regional | Under assessment | 1,440 MW (basis not stated) | No | Verified (official source) | EPBC referral 2026/10667 |
| Bundey Data Centre Campus | SA | IREN | Not stated | Proposed (in planning) | 800 MW (basis not stated) | No | Verified (official source) | EPBC referral 2026/10605 |
| Firmus AI Factory Stirling North (Project Southgate) | SA | Firmus Technologies | Not stated | Proposed (pre-lodgement) | 1,300 MW (IT capacity) | No | Operator-disclosed only | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): Firmus AI Factory Stirling North (Project Southgate) (CSV) |
| Firmus AI Factory Tailem Bend (Project Southgate) | SA | Firmus Technologies | Coorong | Proposed (pre-lodgement) | 1,000 MW (IT capacity) | No | Verified (official source) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): Firmus AI Factory Tailem Bend (Project Southgate) (CSV) |
| Proposed AI data centre / factory, Cooke Plains | SA | Not stated in official source | Coorong | Proposed (pre-lodgement) | Not stated | No | Verified (official source) | Coorong District Council public statement (12 Nov 2026) |
| Quantum DC Tungkillo Compute and Energy Hub | SA | Quantum DC Pty Ltd | Mid Murray | Paused (pre-lodgement) | Not stated | No | Operator-disclosed only | Quantum DC media release, 12 Nov 2026 |
| VIRIDIS Burnie edge data centre | TAS | VIRIDIS Green Data Centres Limited | Burnie | Approved (reported by developer) | Not stated | No | Operator-disclosed only | VIRIDIS: Tasmanian data centre development given planning approval |
| Wesley Vale Data Centre | TAS | Firmus Technologies | Latrobe | Proposed (in planning) | Not stated | No | Verified (official source) | Tas State Planning Office major projects consultations |
| AirTrunk MEL2, Tullamarine (ministerial permit PA2403452) | VIC | EMKC3 Pty Ltd | Not stated | Approved | Not stated | No | Verified (official source) | Vic ministerial permit PA2403452 |
| CDC Laverton Campus | VIC | CDC Data Centres | Not stated | Under construction | 400 MW (basis not stated) | No | Operator-disclosed only | CDC Data Centres website |
| Data centre campus (7 parcels), 45 Donnybrook Road, Mickleham (PA2604506) | VIC | AirTrunk (reported buyer; applicant entity per index AirTrunk MEL3 Pty Ltd) | Hume | Under assessment (reported) | Not stated | No | Lead only (unverified) | Certified Strategic, 25 Jul 2026 |
| Data centre, 148-248 Leakes Road, Truganina† | VIC | Not stated | Wyndham | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit wyndWYP12144/20 |
| Data centre, 165 Williamsons Road, South Morang (ministerial permit PA2604586) | VIC | Dover1 SM2 Pty Ltd | Whittlesea | Under assessment | Not stated | Yes | Verified (official source) | Vic ministerial permit PA2604586 |
| Data centre, 176 Paramount Boulevard, Derrimut† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2010.00000903.001 |
| Data centre, 176 Swann Drive, Derrimut† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2016.00000490.001 |
| Data centre, 1816-1832 Dandenong Road, Clayton† | VIC | Not stated | Monash | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit TPA/39859 |
| Data centre, 20 Hewitt Way, Tullamarine† | VIC | Not stated | Hume | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit humeP17837 |
| Data centre, 210 Swann Drive, Derrimut† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2019.00000082.001 |
| Data centre, 25 Indwe Street, West Footscray† | VIC | Not stated | Maribyrnong | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2020.00000550.001 |
| Data centre, 25-37 Huntingdale Road, Burwood† | VIC | Not stated | Monash | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit TPA/35891 |
| Data centre, 279-295 Ferntree Gully Road, Mount Waverley† | VIC | Not stated | Monash | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit TPA/42637 |
| Data centre, 286-292 Lorimer Street, Port Melbourne† | VIC | Not stated | Melbourne | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit TP-2018-650 |
| Data centre, 3-5 Summit Road, Noble Park North† | VIC | Not stated | Greater Dandenong | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit gdanPLN09/0352 |
| Data centre, 399 Palmers Road, Truganina† | VIC | Not stated | Wyndham | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit wyndWYP12876/21 |
| Data centre, 416 Foleys Road, Derrimut† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2010.00000035.001 |
| Data centre, 43-45 Tullamarine Park Road, Tullamarine† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2021.00000435.001 |
| Data centre, 54 Radnor Drive, Deer Park† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2019.00000505.001 |
| Data centre, 552-578 Lorimer Street, Port Melbourne† | VIC | Not stated | Melbourne | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit PA1600153 |
| Data centre, 552-600 Lorimer Street, Fishermans Bend† | VIC | Not stated | Melbourne | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit TP-2012-1007 |
| Data centre, 585 Berwick-Cranbourne Road, Clyde North (Casey permit PA26-0190) | VIC | Not named by council | Casey | Under assessment | Not stated | Yes | Verified (official source) | City of Casey: Update on planning permit application - Data centre, Clyde North (30 Oct 2026) |
| Data centre, 72 Radnor Drive, Deer Park† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2011.00000582.001 |
| Data centre, 75 Sharps Road, Tullamarine† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2016.00000589.001 |
| Data centre, 826-846 Lorimer Street, Port Melbourne† | VIC | Not stated | Melbourne | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit TP-2010-964 |
| Data centre, 98 Radnor Drive, Deer Park† | VIC | Not stated | Brimbank | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit 005.2011.00000581.001 |
| Data centre, Craigieburn (ministerial permit PA2403014) | VIC | Not stated (see applicant note) | Not stated | Approved | Not stated | No | Verified (official source) | Vic ministerial permit PA2403014 |
| Data centre, McDonalds Road and Plenty Road, South Morang (ministerial permit PA2402997) | VIC | PVAC Development Pty Ltd C/o Planning & Property Partners Pty Ltd | Whittlesea | Approved | Not stated | Yes | Verified (official source) | Vic ministerial permit PA2402997 |
| Data centre, Truganina (ministerial permit PA2403416) | VIC | Aurecon | Not stated | Approved | Not stated | No | Verified (official source) | Vic ministerial permit PA2403416 |
| Data centre, West Footscray (ministerial permit PA2403320) | VIC | Contour Consultants Aust Pty Ltd | Not stated | Approved | Not stated | No | Verified (official source) | Vic ministerial permit PA2403320 |
| Data centre, Wests Road, Werribee† | VIC | Not stated | Wyndham | Approved (permit issued; construction status not checked) | Not stated | Yes | Verified (official source) | Victorian Planning Permit Activity Reporting System (Department of Transport and Planning), permit wyndWYP1072.03 |
| Digital Realty MEL12, Deer Park | VIC | Digital Realty | Brimbank | Proposed (press) | Not stated | No | Lead only (unverified) | iTnews |
| Goodman data centre, 433 Mount Atkinson Road, Truganina (PA2604503) | VIC | Goodman Property Services (Aust) Pty Ltd | Melton | Under assessment (reported) | Not stated | No | Lead only (unverified) | Certified Strategic, 25 Jul 2026 |
| GreenSquareDC MEL1, Spotswood (ministerial permit PA2604553) | VIC | GreenSquare DC | Hobsons Bay | Under assessment | 240 MW (basis not stated) | No | Verified (official source) | Vic ministerial permit PA2604553 |
| Keppel Hazelwood North (Morwell) data centre campus | VIC | Keppel | Latrobe | Proposed (pre-lodgement) | 720 MW (potential power access, not IT load) | No | Verified (official source) | Latrobe City Council: Proposed developments in our region |
| Microsoft data centre, Cawley Road, Yarraville | VIC | Microsoft | Maribyrnong | Proposed (lodged, press) | Not stated | No | Lead only (unverified) | The Urban Developer |
| Microsoft data centre, Woods Road, Truganina | VIC | Microsoft | Wyndham | Under construction (operator) | Not stated | No | Operator-disclosed only | Microsoft: Woods Road datacentre construction overview |
| NEXTDC Craigieburn land | VIC | NEXTDC | Hume | Proposed (land acquired, press) | Not stated | No | Lead only (unverified) | Real Estate Source |
| NEXTDC data centre, 148-158 O’Briens Road, Corio (ministerial permit PA2503895) | VIC | Next DC | Greater Geelong | Approved | Not stated | Yes | Verified (official source) | Vic ministerial permit PA2503895 |
| NEXTDC GE1 Geelong | VIC | NEXTDC | Not stated | In development (operator term) | 4.4 MW (basis not stated) | No | Operator-disclosed only | NEXTDC website |
| NEXTDC M3 expansion, West Footscray (ministerial permit PA2604231) | VIC | NEXTDC Limited | Maribyrnong | Under assessment | Not stated | Yes | Verified (official source) | Vic ministerial permit PA2604231 |
| NEXTDC M4 Port Melbourne (ministerial permit PA2504019) | VIC | NEXTDC Limited | Melbourne | Approved | 150 MW (basis not stated) | No | Verified (official source) | Vic ministerial permit PA2504019 |
| PGIM data centre, 1 Oroya Drive, Truganina (ministerial permit PA2504032) | VIC | The Trust Company (Australia) Limited as trustee of GDCF Truganina Trust | Melton | Approved | Not stated | Yes | Verified (official source) | Vic ministerial permit PA2504032 |
| Plumpton data centre proposal (Syncline Energy) | VIC | Syncline Energy | Melton | Proposed (announced, press) | Not stated | No | Lead only (unverified) | Green Left: communities speak out against vast AI data centre expansion |
| Proposed commercial construction of a data centre (EPBC referral) | VIC | Not stated in EPBC layer | Not stated | Proposed (in planning) | Not stated | No | Official referral, identity unconfirmed | EPBC referral 2026/10668 |
| Stockland Brooklyn data centre, 413 Francis Street (ministerial permit PA2604419) | VIC | Stockland Development Pty Ltd | Hobsons Bay | Under assessment | 250 MVA (electrical supply (MVA)) | Yes | Verified (official source) | Vic ministerial permit PA2604419 |
| Stockland data centre, 72-76 Cherry Lane, Laverton North (ministerial permit PA2604378) | VIC | Stockland Development Pty Ltd | Hobsons Bay | Under assessment | 250 MVA (electrical supply (MVA)) | Yes | Verified (official source) | Vic ministerial permit PA2604378 |
| Warehouse and data centre, 140-204 Western Avenue, Westmeadows (permits PA2302140, PA2302142, PA2302143) | VIC | Not stated in Gazette | Hume | Approved | Not stated | Yes | Verified (official source) | Victoria Government Gazette S697, 21 Dec 2023 |
| Zerra DC Campbellfield campus, 300-340 Barry Road (ministerial permit PA2604362) | VIC | Zerra DC | Hume | Under assessment | Not stated | Yes | Verified (official source) | Vic ministerial permit PA2604362 |
| CDC Hazelmere data centre, 178 and 196 Bushmead Road (City of Swan DA-386/2026) | WA | CDC Data Centres | Swan | Under assessment | Not stated | Yes | Verified (official source) | City of Swan, Swan Engage: DA-386/2026 Proposed Data Centre |
| CDC Maddington Campus | WA | CDC Data Centres | Gosnells | Under construction | 150 MW (IT capacity) | No | Verified (official source) | CDC Data Centres website |
| Data Centre and Ancillary Office, 92 Windsor Road, Wangara (City of Wanneroo DA2022/157) | WA | Not stated | Wanneroo | Under assessment (2022; determination not found) | Not stated | Yes | Verified (official source) | City of Wanneroo consultation page DA2022/157 (Wayback Machine copy, 7 May 2025) |
| Data Centre at 37 Abernethy Road, Belmont (DAP/22/02272) | WA | Not stated in source | Belmont | Approved (press; official minutes archived) | Not stated | Yes | Verified (official source) | Belmont DAP Part B, 28 Mar 2024 |
| Meridien - Renewable Energy Hub and Data Centre | WA | Not stated in EPBC layer | Not stated | Proposed (in planning) | Not stated | No | Verified (official source) | EPBC referral 2026/10654 |
| NEXTDC P1 Stage Two data centre, Malaga (DAP/24/02641) | WA | NEXTDC (presented to the DAP; planning consultant Urbis) | Swan | Approved | Not stated | Yes | Verified (official source) | MODAP/11 minutes, 8 May 2024 (City of Cockburn copy) |
| NEXTDC P2 Perth, 11 Newcastle Street: amendment to data centre approval (City of Perth DA-2024/5403) | WA | Not stated in council list; NEXTDC operates P2 at this address | Perth | Approved (amendment) | Not stated | Yes | Verified (official source) | City of Perth planning approvals issued 14/05/2025–20/05/2025 |
| 52 Turner Road Data Centre | NSW | ARUP PTY LIMITED | Camden | Withdrawn | 40 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-60185233 |
| Augusta Street Data Centre | NSW | AIR TRUNK PTY LTD | Blacktown | Withdrawn | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10469 |
| Mowbray Road Data Centre | NSW | Arup Pty Limited | Lane Cove | Withdrawn | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-13475973 |
| Project Mars Data Centre | NSW | Goodman | Lane Cove | Withdrawn | 90 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-82052708 |
| Waterloo Road Data Centre (ESR Developments) | NSW | ESR Developments | City of Ryde | SEARs expired | Not stated | No | Verified (official source) | NSW Major Projects: SSD-59516710 |
| Centuria Clayton data centre, 1816-1832 Dandenong Road (Monash TPA/57779) | VIC | Centuria Industrial REIT | Monash | Refused | Not stated | No | Lead only (unverified) | Certified Strategic: Monash refuses Centuria Clayton data centre |
| GreenSquareDC WAi1 Hazelmere, Stirling Crescent (City of Swan DA-6/2026) | WA | GreenSquareDC | Swan | Withdrawn | Not stated | Yes | Lead only (unverified) | WAtoday, 14 May 2026 |
† Victorian council planning permit records. They are shown here as facts in our own words, with a link to the source, but they are not in the CSV download.
Status key: Planned (hollow circle on the map) · Under construction (filled teal square on the map) · Withdrawn, refused or expired (not on the map). Planned = proposed or approved, not yet under construction.
Download the Australian data centre dataset
Download the data (CSV, 116 rows)
The CSV has 116 rows. It leaves out the 22 Victorian council planning permit rows marked † in the table. The licence notice explains why.