New South Wales data centre projects
| Project | Developer or applicant | Local government area | Status | Stated capacity | Planning application lodged | Verification | Source |
|---|---|---|---|---|---|---|---|
| 1-5 Khartoum Road Data Centre | Stockland Development Pty Ltd | City of Ryde | Approved | 35 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-63235720 |
| 192 Narellan Road Data Centre, Campbelltown | Morehuman Property Group Pty Ltd | Campbelltown | Proposed (in planning) | 100 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-150514738 |
| 23-25 Waterloo Road Data Centre | Greenbox Architecture Pty Ltd | City of Ryde | Proposed (in planning) | 70 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-91297457 |
| 43-61 Turner Road Data Centre | ARUP PTY LIMITED | Camden | Approved | 53 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-68013714 |
| 51 Huntingwood Drive Data Centre | EMKC CUBED MANAGEMENT PTY LTD | Blacktown | Approved | 400 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-41589232 |
| Aldington Road Data Centre | The Trustee for Fife Land 3 Trust | Penrith | Proposed (in planning) | 444 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-112059740 |
| Apollo Place Data Centre | EMKC Cubed Management Pty Ltd | Lane Cove | Approved | 45 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-67407231 |
| Ashfords Road Data Centre, Gregadoo | CDC Data Centres | Wagga Wagga City | Proposed (in planning) | 1,400 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-144289240 |
| Brookhollow Avenue Data Centre Expansion, Norwest | GreenSquare DC c/- Patch Planning | The Hills Shire | Proposed (in planning) | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-81928961 |
| CDC Data Centre Campus, Kemps Creek | CDC Data Centres | Penrith | Proposed (in planning) | 1,400 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-133677993 |
| Davis Road Data Centre (Cundall) | Cundall Johnston and Partners Pty Limited | Fairfield City | Approved | 180 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-59416728 |
| DCI Poplars Data Centre Project | DCI | Queanbeyan-Palerang Regional | Approved | 25.4 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-64287712 |
| DigiCo SYD1 Data Centre Expansion | DigiCo | City of Sydney | Approved | 47.5 MW (increase in power consumption only) | Yes | Verified (official source) | NSW Major Projects: SSD-69637456 |
| Eastern Creek Data Centre | Woolworths Limited | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0108 |
| Eastern Creek Data Centre Expansion Project | NineZero DC Sub TC I Pty Ltd | Blacktown | Approved | 70.2 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-21342738 |
| EdgeConneX / Stockland MPark Stage 2 | EdgeConneX | Not stated | Proposed (announced) | 100 MW (basis not stated) | No | Lead only (unverified) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): EdgeConneX / Stockland MPark Stage 2 (CSV) |
| Erskine Park Data Centre | Woolworths Limited | Penrith | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0109 |
| Frederick Street Data Centre | Gateway Capital Holdings Pty Ltd | Willoughby City | Proposed (in planning) | 81 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-139545990 |
| Glendenning Road Data Centre | LEHR CONSULTANTS INTERNATIONAL (AUSTRALIA) PTY LTD | Blacktown | Approved | 202.4 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-73761707 |
| Global Switch Data Facility | Global Switch | City of Sydney | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0222 |
| Grand Avenue Data Centre Expansion, Rosehill | Equinix Hyperscale 2 (Sy10) Pty Ltd | City of Parramatta | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-53338465 |
| Hewlett Packard Data Facility | Hewlett Packard | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP10_0142 |
| Honeman Close Data Centre | LEHR Consultants International (Australia) Pty Ltd | Blacktown | Approved | 96 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-58601963 |
| Julius Avenue Data Centre | ISPT PTY LTD | City of Ryde | Proposed (in planning) | 170 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-80018208 |
| Kemps Creek Data Centre | ARUP PTY LIMITED | Penrith | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10101987 |
| Kurri Kurri Data Centre | ADW Johnson Pty Limited | Cessnock City | Proposed (in planning) | 550.5 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-128819490 |
| Lanceley Place Data Centre, Artarmon | Goodman Property Services (AUST) PTY LIMITED | Willoughby City | Approved | 80 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-66777221 |
| Lane Cove West Data Centre | Greenbox Architecture Pty Ltd | Lane Cove | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-9741 |
| Lucca Road Data Centre Wyong | DCG Admin Pty Ltd | Central Coast | Proposed (in planning) | 96 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-148199991 |
| Macquarie Data Centres Sydney North 200 MW campus | Macquarie Data Centres | Not stated | Proposed (announced) | 200 MW (basis not stated) | No | Lead only (unverified) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): Macquarie Data Centres Sydney North 200 MW campus (CSV) |
| Macquarie Engineering and Technology Campus | MDC NEW SITE SUBTST PTY LTD | City of Ryde | Proposed (in planning) | Not stated | No | Verified (official source) | NSW Major Projects: SSD-151494240 |
| Macquarie IC3 Super West | Macquarie Data Centres | Not stated | Under construction | 47 MW (basis not stated) | No | Lead only (unverified) | Megawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): Macquarie IC3 Super West (CSV) |
| Macquarie Park Data Centre | Stockland Corporation Ltd | City of Ryde | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10467 |
| Mamre Road Data Centre Campus | Plan Project Management Pty Ltd | Penrith | Proposed (in planning) | 1,000 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-92743706 |
| Mars Road Data Centre | Willowtree Planning (NSW) Pty Ltd | Lane Cove | Proposed (in planning) | 140 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-108835458 |
| Marsden Park Data Centre | CDC Data Centres | Blacktown | Under construction | 504 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-70889211 |
| Mod 4 - Data Centre | DEXUS Funds Management Limited (proponent of MP 08_0259); facility known as the Fujitsu Data Centre | Cumberland | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: MP08_0259-Mod-4 |
| NEXTDC S4 Data Centre Horsley Park | NEXTDC | Fairfield City | Approved | 250 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-63741210 |
| NEXTDC S4 Data Centre Phase 2, Horsley Park | NEXTDC | Fairfield City | Proposed (in planning) | 134.4 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-108864209 |
| NEXTDC S5 Data Centre and Innovation Hub | NEXTDC | City of Ryde | Proposed (in planning) | 80 MW (IT capacity) | Yes | Verified (official source) | NSW Major Projects: SSD-63168959 |
| NEXTDC S7 Data Centre, Eastern Creek | NEXTDC | Blacktown | Proposed (in planning) | 612 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-113934740 |
| Project Apollo Data Centre Macquarie Park | Goodman Property Services (Aust) Pty Limited | City of Ryde | Approved | 90 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-74069708 |
| Project Atlas Data Centre Eastern Creek | Goodman Property Services (Aust) Pty Ltd | Blacktown | Proposed (in planning) | 500 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-101067971 |
| Project Duke Data Centre | Goodman Property Services (Aust) Pty Ltd | Bayside | Approved | 90 MVA (electrical supply (MVA)) | Yes | Verified (official source) | NSW Major Projects: SSD-71368959 |
| Project Echidna Data Centre Eastern Creek | ARUP AUSTRALIA PTY LTD | Blacktown | Approved | 35 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-47320208 |
| Project Pluto Data Centre | GOODMAN PROPERTY SERVICES (AUST) PTY LIMITED | Cumberland | Approved | 100 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-69223466 |
| Redbank Data Centre | IREN | Wagga Wagga City | Proposed (in planning) | 900 MW (power consumption) | No | Verified (official source) | NSW Major Projects: SSD-155572991 |
| Road 1 Data Centre | Stockland Development Pty Ltd | City of Ryde | Approved | 34.3 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-80814238 |
| Roberts Road Data Centre | Hindmarsh Construction Australia Pty Ltd | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10330 |
| STACK SYD01 Data Centre, Erskine Park | STACK Infrastructure | Penrith | Proposed (in planning) | 450 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-82211208 |
| Station Road Data Centre Expansion | Lehr Consultants International (Australia) Pty Ltd | Blacktown | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-33781208 |
| SYD01 (Huntingwood) Data Centre (EPBC referral) | Not stated in EPBC layer | Not stated | Proposed (in planning) | Not stated | No | Verified (official source) | EPBC referral 2025/10391 |
| Talavera Road Data Centre Campus Expansion | Macquarie Data Centres c/‐ GIDDIS Project Management | City of Ryde | Approved | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-24299707 |
| Wetherill Park Data Centre | Stockland | Fairfield City | Proposed (in planning) | 238 MW (basis not stated) | No | Verified (official source) | NSW Major Projects: SSD-153190740 |
| 52 Turner Road Data Centre | ARUP PTY LIMITED | Camden | Withdrawn | 40 MW (basis not stated) | Yes | Verified (official source) | NSW Major Projects: SSD-60185233 |
| Augusta Street Data Centre | AIR TRUNK PTY LTD | Blacktown | Withdrawn | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-10469 |
| Mowbray Road Data Centre | Arup Pty Limited | Lane Cove | Withdrawn | Not stated | Yes | Verified (official source) | NSW Major Projects: SSD-13475973 |
| Project Mars Data Centre | Goodman | Lane Cove | Withdrawn | 90 MW (power consumption) | Yes | Verified (official source) | NSW Major Projects: SSD-82052708 |
| Waterloo Road Data Centre (ESR Developments) | ESR Developments | City of Ryde | SEARs expired | Not stated | No | Verified (official source) | NSW Major Projects: SSD-59516710 |
Status key: Planned · Under construction · Withdrawn, refused or expired. Planned = proposed or approved, not yet under construction.
Capacity is shown only as the source states it, with its basis (for example power consumption, IT capacity or MVA). Figures with different bases are not added together.