Data centres in Queensland

As at 23 November 2026, we track 9 active data centre projects in Queensland, and 2 of them have a lodged planning application.

Queensland data centre projects

Data centre projects in Queensland, as at 23 November 2026
ProjectDeveloper or applicantLocal government areaStatusStated capacityPlanning application lodgedVerificationSource
DigiCo BNE3DigiCo REITNot statedUnder construction19.6 MW (basis not stated)NoOperator-disclosed onlyMegawattlas project tracker, snapshot 2026-11-15 (CC BY 4.0): DigiCo BNE3 (CSV)
Latan Data Centre and Renewable Energy ProjectAEWC (Australian Energy and Water Corporation)Charters Towers RegionalProposed (announced)100 MW (basis not stated)NoVerified (official source)Qld North Queensland Major Projects Pipeline
NEXTDC Fortitude Valley HQ and data centre expansion (Brisbane A006964285)NEXTDC LimitedBrisbaneApprovedNot statedYesVerified (official source)Brisbane Development.i A006964285
NEXTDC GC1 Gold CoastNEXTDCNot statedIn planning (operator term)6 MW (basis not stated)NoOperator-disclosed onlyNEXTDC website
NEXTDC SC2 Sunshine CoastNEXTDC LimitedSunshine CoastApproved; under construction (operator)6 MW (basis not stated)NoVerified (official source)EDQ development assessment DEV2025/1604
Quinbrook Supernode, BrendaleQuinbrook Infrastructure PartnersMoreton BayApproved (council planning and FIRB, per Qld media statement 8 Jul 2022)Not statedNoVerified (official source)Qld ministerial media statement 95682 (8 Jul 2022)
Swanbank data centre, Six Leaf Street (Ipswich 12285/2026/MCU)Northern Concept Swanb Pty LtdIpswichUnder assessmentNot statedYesVerified (official source)Ipswich Development.i 12285/2026/MCU
Wellcamp data centre expansion, 65 Witmack Road (Toowoomba MCUC/2016/2385/E)Centuria (owner, per ASX results); applicant not confirmedToowoomba RegionalApproved (change application, reported)Not statedNoLead only (unverified)PlanningAlerts: 65 Witmack Road Wellcamp
Western Downs Digital ParkZerra DCWestern Downs RegionalUnder assessment1,440 MW (basis not stated)NoVerified (official source)EPBC referral 2026/10667

Status key: Planned · Under construction · Withdrawn, refused or expired. Planned = proposed or approved, not yet under construction.

Capacity is shown only as the source states it, with its basis (for example power consumption, IT capacity or MVA). Figures with different bases are not added together.