When is a Section J report required?

A Section J report is usually required for any new Class 2 to 9 building, and for alterations, extensions, changes of use and fit-outs to existing commercial buildings where the new work must comply with the NCC. The building surveyor or certifier asks for it at building permit stage, but the decisions it tests are made much earlier. This guide sets out the triggers by type of work, what changes between states, and when to bring in a Section J consultant.
Why it matters
Most teams find out they need a Section J report when the building surveyor or certifier asks for it. By then the glazing ratio, roof, plant strategy and fit-out scope are drawn and priced, so a shortfall means redesign, a delayed permit or an expensive specification upgrade. Knowing the trigger at concept stage lets you test those decisions while they are still cheap to change.
When is a Section J report required?
Short answer: you will usually need a Section J report for any new Class 2 to 9 building, and for alterations, extensions and changes of use to an existing commercial building where the new work must comply with the NCC. The building surveyor or certifier asks for it before issuing the building permit, construction certificate or equivalent approval.
Section J (Energy Efficiency) of NCC Volume One applies to Class 2 to 9 buildings (NCC 2022 J2D2). Under NCC 2025, J2D2 covers Class 3 to 9 buildings, and Class 2 buildings use Section J of NCC 2022 Amendment 2 instead (NCC 2025 Part J1, Notes). Houses (Class 1) and Class 10 structures such as sheds and carports are not covered by Section J.
| Type of work | Section J report usually required? | Stage it is needed |
|---|---|---|
| New Class 3, 5, 6, 7, 8 or 9 building | Yes | Building permit or construction certificate. Test the design at concept and schematic design |
| New Class 2 apartment building (common areas and building services) | Yes, under the Class 2 provisions | Building permit. Sole-occupancy units are assessed by a separate route |
| Extension to a commercial building | Yes, for the new part. In some states, for example Victoria, a large extension can bring the existing building in | Building permit. Check the size of the extension at concept |
| Alteration or refurbishment of a commercial building | Usually, for the new work. Extent decides how much of the existing building is in scope | Building permit |
| Change of use, for example warehouse to office | Often. Depends on the new classification and state law | Before the change of use is approved |
| Tenancy fit-out | Often, for new lighting, air-conditioning and sealing work | Building permit for the fit-out |
| Like-for-like repair or maintenance | Usually not | Confirm with the building surveyor or certifier |
| Town planning application | Not as a Section J report. Many councils ask for an ESD report that relies on Section J decisions | Planning submission |
The building surveyor or certifier makes the final call on what is in scope, under the law of your state or territory. Use the table to plan, then confirm the scope with them early.
Do I need a Section J report for a building permit?
Yes, for most commercial work. Section J is a building approval requirement. The building surveyor or certifier needs evidence that the design meets the Section J Performance Requirements, including J1P1, before they approve the building work. A Section J report is the usual form of that evidence.
In New South Wales, for example, a certifier must not issue a construction certificate unless the building will comply with the relevant requirements of the Building Code of Australia in force on the relevant date, which is usually the date of the construction certificate application (Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021, s 19(1)(c) and (1A)). Section J is part of those requirements.
The report supports the building approval. It is not the approval itself.
Is a Section J report required at town planning?
Not usually as a formal Section J report. But the decisions a Section J report tests are often made at town planning.
In Victoria, many councils ask for a sustainability report, such as a Sustainability Management Plan (SMP), with the planning application. These reports commit the project to an energy approach, and planning permit conditions can carry those commitments through to the building permit. Other states use their own ESD or sustainability reports at planning stage.
If the facade, glazing ratio or roof layout is fixed at planning without a Section J check, the building permit stage can force a choice between expensive glazing, modelling or an amended planning permit. A preliminary Section J review at planning stage avoids that rework. It is design advice, not the final compliance report.
Do alterations and renovations need a Section J report?
Often, yes. For commercial buildings, the extent of the new work decides how much of the building must comply.
The NCC defines an alteration, in relation to a building, as including an addition or extension (NCC 2022 Schedule 1). How far the NCC then applies to the existing building is set by state and territory law, not by Section J itself.
Victoria shows how this works:
- Building work to alter an existing building must comply with the Building Regulations 2018, which call up the NCC (reg 233(1)).
- If the proposed alterations, together with other alterations completed or permitted in the previous 3 years, relate to more than half the original volume of the building, the entire building must be brought into conformity, subject to regs 234 and 236 (reg 233(2)).
- The relevant building surveyor may consent to partial compliance (reg 233(3)), recorded on Form 18.
So a refurbishment of one floor of an office building will usually need Section J for the new lighting, air-conditioning and any new envelope work. A whole-building refurbishment can put the existing envelope and services in scope too.
In the ACT, plans for a substantial alteration must show that the building as altered will comply with the Building Act 2004 and the building code (s 29(1)(a)). Regulations decide what counts as a substantial alteration.
Other states and territories set their own rules for how far an alteration brings the existing building up to the current NCC. Ask your building surveyor or certifier to confirm the extent before design development.
Does an extension need a Section J report?
Yes. An extension is new building work, so the extension itself must meet Section J. The open question is whether the existing building is drawn in as well.
In Victoria, the building surveyor can only consent to partial compliance for an extension if its floor area is not greater than the lesser of 25% of the floor area of the existing building or 1,000 m² (Building Regulations 2018, reg 233(6)). Above that size, the extension must comply in full.
For design teams, the practical point is the junction. New glazing, a new roof plane or a new air-conditioning system serving both old and new parts can widen the scope. Agree the boundary of the assessment with the building surveyor before the extension is documented.
Does a change of use need Section J?
It can, even with little building work. A change of use can change the building's NCC classification, and Section J requirements differ by class. A Class 7b warehouse that becomes a Class 5 office goes from storage use to an occupied, air-conditioned workplace, with different lighting, air-conditioning and envelope requirements. Retail to gym is another common example. A shop is Class 6. The NCC's assembly building definition covers buildings used for recreational or sporting purposes, so a gym is often classified as Class 9b, but the building surveyor or certifier decides the classification.
The NCC applies Section J's building fabric provisions to the envelope, which it defines around conditioned spaces and habitable rooms (NCC 2022 and NCC 2025 Schedule 1, "envelope"; application of Part J4 building fabric provisions in J4D2). A change of use that adds air-conditioning can therefore create an envelope where none was assessed before.
State law decides whether the existing building must be upgraded:
- Victoria: a person must not change the use of a building unless it complies with the requirements of the Building Regulations 2018 applicable to the new use. The municipal building surveyor, or a private building surveyor appointed to issue the occupancy permit, may grant an exemption (regs 229 and 230).
- New South Wales: where building work is carried out under a development consent that authorises a change of building use, the certifier must be satisfied that the fire protection and structural capacity suit the new use and that the Category 1 fire safety provisions are met (s 14(1)). The building work must comply with the BCA (s 19).
In New South Wales and other states, a change of use can lead to upgrade requirements, mainly for fire safety. Whether Section J applies to the existing fabric and services depends on state law and the approval conditions, so confirm it with the certifier or building surveyor early.
What about fit-outs and tenancy works?
A commercial fit-out that is building work usually needs Section J for the new work: typically lighting and power (Part J7), air-conditioning and ventilation (Part J6), and building sealing (Part J5) where new work affects the envelope. A shell-and-core building approved without a fit-out does not settle the tenancy's Section J compliance.
Two traps come up often. First, lighting layouts and controls are set late, by the tenant's designer, and are a common reason a fit-out fails Section J. Second, a fit-out that adds air-conditioning to a space that was previously unconditioned may bring the surrounding walls, roof and glazing into scope.
In Victoria, some minor non-structural alterations are exempt from a building permit if they meet every condition in Schedule 3 of the Building Regulations 2018. Examples are no structural change, no change to floor area or height, and no effect on essential safety measures. Work on a Heritage Register building is not exempt.
Each state sets its own exemptions for minor works. If a fit-out includes new lighting, air-conditioning or work that affects fire safety, assume a permit is needed until your building surveyor or certifier confirms otherwise.
Are there exemptions?
There is no general exemption from Section J for a new Class 3 to 9 building. The exemptions and limitations that exist are narrower:
- Building classes outside Section J. Section J covers Class 2 to 9 buildings. Under NCC 2025, Class 2 buildings still use the NCC 2022 Amendment 2 version of Section J. Class 1 houses and Class 10 structures are outside it.
- Limitations inside individual provisions. Many Section J provisions have their own limitations. For example, the NCC 2025 on-site solar PV requirement in J9D5(2) does not apply where 100% of the effective roof area is shaded for more than 70% of annual daylight hours.
- Unconditioned spaces. The envelope is defined around conditioned spaces and habitable rooms, so an unconditioned warehouse or car park may have little or no envelope to assess. Lighting and power (Part J7) still apply, and so do air-conditioning and ventilation (Part J6) for any system that is installed. In these Parts the NCC only excludes a Class 8 electricity network substation (NCC 2025 J6D2, J7D2).
- Building surveyor discretion on existing buildings. In Victoria, partial compliance for alterations (reg 233(3)) and exemptions on a change of use (regs 229 and 230) are decisions for the building surveyor, recorded on Form 18. They are not automatic.
- Heritage buildings. Heritage fabric that cannot meet a Deemed-to-Satisfy Provision is normally handled with a Performance Solution, not an exemption.
- Temporary buildings. Some states exempt temporary buildings and structures from the building permit or BCA requirements, for example Victoria (Building Regulations 2018, Sch 3 items 6 and 7) and New South Wales (s 19(2)(a)). Rules differ by state.
Does it differ by state?
Yes. The NCC is adopted by each state and territory, and some replace or vary Section J. The edition that applies also depends on the date of your application.
| State or territory | NCC 2025 adoption | What to watch for Section J |
|---|---|---|
| Victoria | 1 May 2026 | NCC 2025 Section J for Class 3 and 5 to 9 |
| ACT | 1 May 2026, 12-month transition | Building approvals before 1 May 2027 can use NCC 2022 or NCC 2025 (nominate one). A DA lodged before 1 November 2026 keeps that choice while the DA is valid. |
| Western Australia | 1 May 2026, 12-month transition | Most building permit applications can use BCA 2025 or BCA 2022 (with Amendments 1 and 2) until 30 April 2027. |
| New South Wales | 1 May 2027 | NSW varies Section J in both NCC 2022 and NCC 2025 |
| Queensland | 1 May 2027 | NCC 2025 variations remove the future-electrification provisions for gas space heating and heated water (J6D10, J8D3) |
| South Australia | 1 May 2027 (BCA) | Plumbing Code adopted 1 May 2026; BCA, including Section J, from 1 May 2027 |
| Tasmania | 1 May 2027. NCC 2025 was temporarily adopted from 1 May to 4 June 2026, and a transition runs from 5 June 2026 to 1 May 2027. Check which edition your application falls under. | NCC 2025 replaces Section J with BCA 2022 Amendment 2 for Class 3 and 5 to 9, and BCA 2019 Amendment 1 for Class 2 and Class 4 parts |
| Northern Territory | Not adopted (NCC 2022 applies) | Class 3 and 5 to 9 use NCC 2019 Section J. Class 2 and Class 4 parts use BCA 2009 Section J |
Sources: ABCB, NCC 2025 state and territory adoption information; NCC 2025 Part J1 Notes; NCC 2022 and NCC 2025 NT Part J1; NCC 2022 and NCC 2025 NSW and Queensland variations.
For the detail in each jurisdiction, see NCC 2025 and ESD requirements by state. For Queensland projects, see Section J reports in Queensland and our Queensland NCC 2025 and Section J guide.
What does a Section J report cover?
A Section J report records how the design meets Section J for the edition that applies. Under the Deemed-to-Satisfy route it works through the applicable provisions: building fabric (Part J4), building sealing (Part J5), air-conditioning and ventilation (Part J6), artificial lighting and power (Part J7), heated water supply (Part J8), and energy monitoring and on-site distributed energy resources (Part J9). Under NCC 2025, that includes on-site solar PV unless a J9D5 limitation applies.
For what changed between the editions, see NCC 2025 Section J explained. For what we assess and deliver, see our Section J report service.
Deemed-to-satisfy or performance solution: which do I need?
You do not need to decide before you engage a consultant, but you should decide before documentation.
- Deemed-to-Satisfy (DTS): a solution that complies with the DTS Provisions is deemed to meet the Performance Requirements (NCC 2022 A2G3). Each applicable element meets its own provision. It suits a design that already fits those provisions.
- Performance Solution: shown to comply with the Performance Requirements through an Assessment Method, such as a Verification Method (NCC 2022 A2G2). For Section J this is usually J1V3, which models the proposed building against a reference building. Under NCC 2025, the proposed building's annual greenhouse gas emissions must be not more than 97% of the reference building's, alongside the other J1V3 tests.
Choose DTS when the design can meet the provisions without costly upgrades. Consider J1V3 when a fixed element, such as a highly glazed facade or heritage fabric, fails DTS. For the full comparison, see Section J: DTS vs JV3, which pathway and when and our J1V3 (JV3) energy modelling service.
When should I engage a Section J consultant?
At concept or schematic design, before the planning drawings fix the facade. That is when a short Section J check on glazing, roof and plant strategy costs least and changes most. The second-best time is before design development is locked. The most expensive time is when the building surveyor asks for the report.
Bring your drawings, the building class, the project address and the scope of work. For new buildings, alterations, extensions, changes of use and fit-outs, see our Section J report service.
By the time a report is due, most of the decisions it tests are already drawn and priced. Bring us in while they can still change, and the report confirms the design instead of reshaping it.
FAQ
Who asks for a Section J report?
The building surveyor or certifier. They need evidence that the design meets Section J before they issue the building permit, construction certificate or equivalent approval.
Can a Section J report be done after the building permit?
The report is normally needed before the building permit is issued. If the design changes after approval, for example a glazing or lighting substitution, the Section J assessment may need to be updated and the change approved.
Does an unconditioned warehouse need a Section J report?
It may still need one. Section J's building fabric provisions apply to the envelope, which the NCC defines around conditioned spaces and habitable rooms, so an unconditioned warehouse may have little envelope to assess. Lighting and power (Part J7) still apply, and so do air-conditioning and ventilation (Part J6) for any system that is installed. In these Parts the NCC only excludes a Class 8 electricity network substation (NCC 2025 J6D2, J7D2). The building surveyor or certifier confirms the scope.
Does a change of use with no building work need a Section J report?
It can. In Victoria, a building must comply with the Building Regulations 2018 requirements for its new use before the use changes, unless the municipal building surveyor, or a private building surveyor appointed to issue the occupancy permit, grants an exemption (regs 229 and 230). In New South Wales and other states, a change of use can lead to upgrade requirements, mainly for fire safety. Whether Section J applies to the existing fabric and services depends on state law and the approval conditions, so confirm it with the certifier or building surveyor early.
Which NCC edition does my Section J report use?
It depends on your state or territory and the date of your application. Victoria adopted NCC 2025 on 1 May 2026. The ACT and Western Australia adopted it on 1 May 2026 with a 12-month transition, during which either edition can be used. New South Wales, Queensland and South Australia adopt it on 1 May 2027, and Tasmania is in a transition until 1 May 2027. The Northern Territory has not adopted NCC 2025 and uses NCC 2019 Section J for most commercial buildings.
Questions or corrections: contact Makao.