Standards B5‑1 to B5‑7 sit in Clause 55.05 of the Victoria Planning Provisions. Work through one standard at a time. Each step is labelled as a calculated check, a design input from the drawings or a model, or a judgement call for an assessor.
These two questions decide which standards apply. Everything else lives in the standard it belongs to. Clause 55 applies to the classes of applications listed in the relevant zone (including clauses 32.04‑7, 32.05‑8, 32.07‑6, 32.08‑7, 32.09‑7 and 32.10‑5). Check the current scheme.
[Calculated]
Pervious surfaces are to cover at least 20 percent of the site. The B5‑2 setback is 1 metre at 3.6 metres, then 0.3 metres per metre up to 6.9 metres, then 1 metre per metre above that. Rooftop solar area in Table B5‑3 is 15, 26 or 34 m² with a 1.7 m minimum dimension. North-window shade depth is 0.25 times the window height.
[Design input]
Shadow diagrams for 22 September between 9 am and 4 pm, the roof plan, shade devices, the waste path, and an energy-rating model already prepared for the application are design inputs. This checker does not generate those.
[Judgement call]
Whether plant is immediately adjacent, whether a barrier is a line of sight barrier to transmission of noise, and how “apartment development” is read, are judgement calls. The checker will not guess a climate zone in Table B5‑7.
[Defaults]
If the calculated B5‑2 setback is met, the standard records as Meets*. If plant is not immediately adjacent to bedrooms, B5‑6 records as Meets*. A footnote explains that added justification may be needed in the planning submission.
Every item in the checker is labelled Calculated, Design input or Judgement call.
Indicative only. This is not advice and not a statement that a proposal complies. The responsible authority decides whether a standard and the corresponding objective are met, and a modified standard in a zone, a schedule or an overlay may apply. Results do not account for every overlay or schedule, how council classifies the development, or later amendments. Check the current planning scheme and confirm with council or a qualified consultant.
Clause 55.05 as fetched from the Victoria Planning Provisions API on 18 November 2026. VPP current to VC322 (2 November 2026). Standard B5‑1 last amended by VC315 (24 September 2026); Standards B5‑2 to B5‑7 last amended by VC267.